top of page

Floor Insulation

 
 

Tingvej, Danemark, 2015

 

  1. Excavate and fill with gravel mixture (dia: 5-8 cm) to a thickness of 10cm.

  2. Pose a perforated tube (air drain dia: 4-6 cm) imbedded in gravel.

  3. Add 5 cm of gravel (dia: 3-5cm)

  4. Apply HES-mix on the gravel bed 15-20 cm.

  5. Pose floor heating (if required).

  6. Pose a 6 – 8 cm lime-sand mortar.

Photos © Hemp Eco Systems 2016